MIS LOG IN

NPRR635

Summary

Title Clarification of Congestion Revenue Right Source/Sink Points
Next Group
Next Step
Status Approved on 10/14/2014
Effective Dates
11/01/2014

Action

Date Gov Body Action Taken Next Steps
10/14/2014 BOARD Approved
08/28/2014 TAC Recommended for Approval ERCOT Board for consideration
08/14/2014 PRS Recommended for Approval TAC for consideration.
07/17/2014 PRS Recommended for Approval PRS for IA review.

Voting Record

Date Gov Body Motion Result
10/14/2014 BOARD To approve NPRR635 as recommended by TAC in the 8/28/14 TAC Report Passed
08/28/2014 TAC To recommend approval of NPRR635 as recommended by PRS in the 8/14/14 PRS Report. Passed
08/14/2014 PRS To endorse and forward the 7/17/14 PRS Report and the Impact Analysis for NPRR635 to TAC. Passed
07/17/2014 PRS To recommend approval of NPRR635 as revised by PRS. Passed

Background

Status: Approved
Date Posted: Jun 25, 2014
Sponsor: Boston Energy
Urgent: No
Sections: 3.10.3, 3.10.3.1
Description: This Nodal Protocol Revision Request (NPRR) will establish that Resource Settlement Points are retained in ERCOT Congestion Revenue Right (CRR) and Day-Ahead Market (DAM) models until there is no further Resource association with the Settlement Point.
Reason: Addresses current operational issues and enhances market efficiencies.

Key Documents

Related Content