MIS LOG IN

NPRR649

Summary

Title Addressing Issues Surrounding High Dispatch Limit (HDL) Overrides
Next Group
Next Step
Status Approved on 04/19/2016
Effective Dates
03/09/2017

Action

Date Gov Body Action Taken Next Steps
04/19/2016 BOARD Approved
03/31/2016 TAC Recommended for Approval Board for consideration
02/25/2016 TAC Deferred/Tabled TAC for consideration
02/09/2016 BOARD Remanded TAC for consideration
11/19/2015 TAC Rejected
11/12/2015 PRS Recommended for Approval TAC for consideration
10/15/2015 PRS Recommended for Approval PRS for Impact Analysis review
08/13/2015 PRS Deferred/Tabled PRS for consideration
07/16/2015 PRS Deferred/Tabled PRS for consideration
06/11/2015 PRS Recommended for Approval PRS for Impact Analysis review
03/12/2015 PRS Deferred/Tabled PRS for consideration
10/09/2014 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
04/19/2016 BOARD To approve NPRR649 as recommended by TAC in the 3/31/16 TAC Report and as amended by the 4/7/16 ERCOT comments Passed
03/31/2016 TAC To recommend approval of NPRR649 as recommended by PRS in the 11/12/15 PRS Report and as amended by the 2/22/16 ERCOT comments Passed
02/25/2016 TAC To table NPRR649 Passed
02/09/2016 BOARD To grant the appeal of Koch Ag and remand NPRR649 to TAC, with the following instructions to report back on this matter at the ERCOT Board’s April 2016 meeting: 1. A recommendation of NPRR649 as proposed by Koch Ag in this appeal; or 2. A recommendation of a version of NPRR649 with alternatives for generator financial losses; or 3. If TAC votes not to recommend any version of NPRR649 for ERCOT Board approval, a review (including reasons for disapproval) of the alternatives considered by TAC that did not result in a version of NPRR649 recommended for approval. The ERCOT Board further instructs ERCOT to file comments on NPRR649 to assist TAC in the development of alternatives called for by the ERCOT Board’s remand of the NPRR. Passed
11/19/2015 TAC To recommend approval of NPRR649 as recommended by PRS in the 11/12/15 PRS Report and as revised by TAC Failed
11/12/2015 PRS To endorse and forward to TAC the 10/15/15 PRS Report as amended by the 11/11/15 Odessa-Ector comments and the revised Impact Analysis for NPRR649 with a recommended priority of 2016 and rank of 1520 Passed
10/15/2015 PRS To endorse the 8/13/15 PRS Report as amended by the 9/30/15 ERCOT comments; and requested a revised Impact Analysis be brought back to PRS for consideration Passed
08/13/2015 PRS To table NPRR649 and refer the issue to WMS; and requested that ERCOT consider alternative solutions/language to address the intent of NPRR649 at a lower cost Passed
07/16/2015 PRS To table NPRR649 Passed
06/11/2015 PRS To recommend approval of NPRR649 as amended by the 6/4/15 WMS comments Passed
03/12/2015 PRS To table NPRR649 and to refer the issue to WMS Passed
10/09/2014 PRS To table NPRR649 and to refer the issue to WMS Passed

Background

Status: Approved
Date Posted: Sep 12, 2014
Sponsor: ERCOT
Urgent: No
Sections: 1.3.1.1, 4.6.5, 6.5.7.1.10, 6.5.7.1.13, 6.6.3.9 (new), 6.6.3.10 (new), 6.6.5.1, 9.5.3
Description: This Nodal Protocol Revision Request (NPRR) proposes a compensation mechanism for Generation Resources that are issued a High Dispatch Limit (HDL) manual override that results in a real power reduction (subject to certain criteria). The proposed mechanism compensates the Qualified Scheduling Entity (QSE) for financial loss associated with variable cost components of Day-Ahead Market (DAM) obligations or bilateral contracts arising from the HDL manual override. ERCOT submits this NPRR to satisfy its obligations under a settlement agreement reached with Odessa Ector Power Partners, LP in Public Utility Commission of Texas (PUCT) Docket 41790. ERCOT’s submission of this NPRR does not imply ERCOT’s support for or opposition to the principles stated in this NPRR.
Reason: Submitted pursuant to settlement agreement.

Key Documents

Related Content