NPRR783

Summary

Title Revision of Network Operations Model Consistency Audit Requirement
Next Group
Next Step
Status Approved on 12/13/2016
Effective Dates
01/01/2017

Action

Date Gov Body Action Taken Next Steps
12/13/2016 BOARD Approved
10/27/2016 TAC Recommended for Approval Board for consideration
10/13/2016 PRS Recommended for Approval TAC for consideration
09/15/2016 PRS Recommended for Approval PRS for Impact Analysis review
06/16/2016 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
12/13/2016 BOARD To approve NPRR783 as recommended by TAC in the 10/27/16 TAC Report Passed
10/27/2016 TAC To recommend approval of NPRR783 as recommended by PRS in the 10/13/16 PRS Report Passed
10/13/2016 PRS To endorse and forward to TAC the 9/15/16 PRS Report and Impact Analysis for NPRR783 Passed
09/15/2016 PRS To recommend approval of NPRR783 as submitted Passed
06/16/2016 PRS To table NPRR783 and refer the issue to ROS Passed

Background

Status: Approved
Date Posted: Jun 1, 2016
Sponsor: ERCOT
Urgent: No
Sections: 3.10
Description: This Nodal Protocol Revision Request (NPRR) revises an outdated requirement for an independent audit to confirm consistency between ERCOT operations models, yet retains the underlying requirement of model consistency.
Reason: Addresses current operational issues / regulatory requirement