NPRR799

Summary

Title Updates to Outages of Transmission Facilities
Next Group
Next Step
Status Approved on 04/04/2017
Effective Dates
05/01/2017

Action

Date Gov Body Action Taken Next Steps
04/04/2017 BOARD Approved
03/23/2017 TAC Recommended for Approval Revision Request Consideration
03/09/2017 PRS Recommended for Approval Revision Request Consideration
02/09/2017 PRS Recommended for Approval Impact Analysis Consideration
01/19/2017 PRS Deferred/Tabled Language Consideration
09/15/2016 PRS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
04/04/2017 BOARD Approved NPRR799 as recommended by TAC in the 3/23/17 TAC Report. Passed
03/23/2017 TAC To recommend approval of NPRR799 as recommended by PRS in the 3/9/17 PRS Report. Passed
03/09/2017 PRS To forward to TAC the 2/9/17 PRS Report and the Impact Analysis for NPRR799 Passed
02/09/2017 PRS To recommend approval of NPRR799 as amended by the 1/19/17 Morgan Stanley comments. Passed
01/19/2017 PRS To table NPRR799 for one month. Passed
09/15/2016 PRS To table NPRR799 and refer the issue to ROS and WMS. Passed

Background

Status: Approved
Date Posted: Aug 25, 2016
Sponsor: DC Energy Texas
Urgent: No
Sections: 3.1.2, 3.1.5.13
Description: This Nodal Protocol Revision Request (NPRR) introduces requirements for submitting updates to the Outage Scheduler for completed or started Outages on Transmission Facilities.
Reason: Market efficiencies or enhancements