NPRR806

Summary

Title Clarification for Designation of Capacity or Refund PCRRs
Next Group
Next Step
Status Approved on 02/14/2017
Effective Dates
03/01/2017

Action

Date Gov Body Action Taken Next Steps
02/14/2017 BOARD Approved
01/26/2017 TAC Recommended for Approval Revision Request Consideration
12/01/2016 PRS Recommended for Approval Revision Request Consideration
11/10/2016 PRS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
02/14/2017 BOARD Approved NPRR806 as recommended by TAC in the 1/26/17 TAC Report. Passed
01/26/2017 TAC To recommend approval of NPRR806 as recommended by PRS in the 12/1/16 PRS Report. Passed
12/01/2016 PRS To endorse and forward to TAC the 11/10/16 PRS Report and Impact Analysis for NPRR806. Passed
11/10/2016 PRS To recommend approval of NPRR806 as submitted. Passed

Background

Status: Approved
Date Posted: Oct 6, 2016
Sponsor: ERCOT
Urgent: No
Sections: 7.4.2.2
Description: This Nodal Protocol Revision Request (NPRR) clarifies how Non-Opt-In Entities (NOIEs) are to designate whether they want to accept the refund option or the capacity option for their Pre-Assigned Congestion Revenue Right (PCRR)-eligible Resources. Specifically, it makes clear that the choice of refund or capacity is for the entire PCRR allocation year for each eligible Resource. NOIEs cannot select one option (refund or capacity) for some months of the year and the other option for the remaining months.
Reason: Market efficiencies or enhancements