To endorse and forward to TAC the 8/11/17 PRS Report as amended by the 9/6/17 ERCOT comments and the revised Impact Analysis for NPRR815 with a recommended priority of 2018 and a rank of 2070.
To table NPRR815 and refer the issue to WMS and ROS.
Passed
Background
Status:
Approved
Date Posted:
Jan 24, 2017
Sponsor:
Morgan Stanley
Urgent:
No
Sections:
3.16
Description:
This Nodal Protocol Revision Request (NPRR) revises the current limit of 50% to 60%, and specifies that Primary Frequency Response from Resources shall not be less than 1150 MW.