to table NPRR851 and refer the issue to RMS, ROS, and WMS
Passed
Background
Status:
Approved
Date Posted:
Oct 25, 2017
Sponsor:
Golden Spread Electric Coop, Inc. (GSEC)
Urgent:
No
Sections:
2.1, 3.1.5.1
Description:
This Nodal Protocol Revision Request (NPRR) was developed to fully implement the market design envisioned in NPRR 596, External Load Serving Entities. This NPRR establishes a clearly defined disconnection process within ERCOT market rules applicable to a transmission voltage connection to the ERCOT grid which utilizes one electrical connection for both generation and load services.