MIS LOG IN

NPRR866

Summary

Title Mapping Registered Distributed Generation and Load Resources to Transmission Loads in the Network Operations Model
Next Group
Next Step
Status Approved on 08/07/2018
Effective Dates
04/05/2019

Action

Date Gov Body Action Taken Next Steps
08/07/2018 BOARD Approved
07/26/2018 TAC Recommended for Approval Revision Request Consideration
07/19/2018 PRS Recommended for Approval Revision Request Consideration
06/14/2018 PRS Recommended for Approval Impact Analysis Consideration
03/08/2018 PRS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
08/07/2018 BOARD To approve NPRR866 as recommended by TAC in the 7/26/18 TAC Report. Passed
07/26/2018 TAC To recommend approval of NPRR866 as recommended by PRS in the 7/19/18 PRS Report. Passed
07/19/2018 PRS To endorse and forward to TAC the 6/14/18 PRS Report and Impact Analysis for NPRR866 with a recommended priority of 2018 and a rank of 2270. Passed
06/14/2018 PRS To recommend approval of NPRR866 as amended by the 5/16/18 Oncor comments as revised by PRS. Passed
03/08/2018 PRS To table NPRR866 and to refer the issue to ROS and WMS. Passed

Background

Status: Approved
Date Posted: Feb 14, 2018
Sponsor: ERCOT
Urgent: No
Sections: 3.10.7.2
Description: This Nodal Protocol Revision Request (NPRR) accomplishes two objectives related to mapping registered Distributed Generation (DG) and Load Resources to transmission Loads in the Network Operations Model. Specifically, this NPRR expands paragraph (2) of Section 3.10.7.2 to codify the existing process for mapping a Load Resource or an Aggregate Load Resource (ALR) to its appropriate Load point in the Network Operations Model; and outlines in a new paragraph (3) of Section 3.10.7.2 the practice for mapping a registered DG facility to its appropriate Load point in the Network Operations Model. These changes would affect all existing and future DG facilities that have registered or will register with ERCOT pursuant to paragraph (5) of Section 16.5, Registration of a Resource Entity. DG registration is required for any DG facility with a capacity rating above the registration threshold, currently set at 1 MW, and which injects energy to the distribution grid. Registration with ERCOT is optional for smaller DG facilities.
Reason: Addresses current operational issues; Meets Strategic goals, Market efficiencies or enhancements

Key Documents

Related Content