NPRR869
Summary
Title | Clarification of Language Related to Generation Netting for ERCOT-Polled Settlement Meters |
---|---|
Next Group | |
Next Step | |
Status | Approved on 10/09/2018 |
Effective Dates |
11/01/2018
|
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
10/09/2018 | BOARD | Approved | |
09/26/2018 | TAC | Recommended for Approval | Revision Request Consideration |
09/13/2018 | PRS | Recommended for Approval | Revision Request Consideration |
08/16/2018 | PRS | Recommended for Approval | Impact Analysis Consideration |
05/10/2018 | PRS | Deferred/Tabled | Language Consideration |
04/12/2018 | PRS | Deferred/Tabled | Language Consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
10/09/2018 | BOARD | approved NPRR869 as recommended by TAC in the 9/26/18 TAC Report | Passed |
09/26/2018 | TAC | to recommend approval of NPRR869 as recommended by PRS in the 9/13/18 PRS Report | Passed |
09/13/2018 | PRS | to endorse and forward to TAC the 8/16/18 PRS Report and Impact Analysis for NPRR869 | Passed |
08/16/2018 | PRS | to recommend approval of NPRR869 as amended by the 8/7/18 ERCOT comments | Passed |
05/10/2018 | PRS | to table NPRR869 and refer the issue to WMS | Passed |
04/12/2018 | PRS | to table NPRR869 | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Mar 22, 2018 |
Sponsor: | Reliant Energy Retail Services |
Urgent: | No |
Sections: | 3.10.7.3 and 10.3.2.3 |
Description: | This Nodal Protocol Revision Request (NPRR) requires certain generators over 1 MW (i.e., generators that are not: (i) registered with the Public Utility Commission of Texas (PUCT) as a power generation company; (ii) part of a Private Use Network with more than one connection to the ERCOT Transmission Grid; or (iii) registered to provide Ancillary Services) within a Private Use Network to provide modeling information to ERCOT as set forth in paragraph (1)(b) of Section 3.10.7.3; provides a netting exemption for a Qualifying Facility (QF) that is a small power production facility and lawfully provides energy to a Customer behind a single Point of Interconnection (POI); and deletes a reference to the now-expired system benefit fund charges. |
Reason: | Addresses current operational issues, Meets Strategic goals |
Key Documents
Mar 22, 2018 - doc - 99.5 KB
Apr 12, 2018 - doc - 83.5 KB
May 8, 2018 - doc - 94 KB
May 10, 2018 - doc - 83.5 KB
Jun 7, 2018 - doc - 40.5 KB
Jul 3, 2018 - doc - 71.5 KB
Jul 11, 2018 - doc - 41 KB
Aug 3, 2018 - doc - 69 KB
Aug 7, 2018 - doc - 69.5 KB
Aug 17, 2018 - doc - 93.5 KB
Sep 5, 2018 - doc - 54.5 KB
Sep 19, 2018 - doc - 96 KB
Sep 27, 2018 - doc - 100.5 KB
Oct 9, 2018 - doc - 102 KB