NPRR917
Summary
Title | Nodal Pricing for Settlement Only Distribution Generators (SODGs) and Settlement Only Transmission Generators (SOTGs) |
---|---|
Next Group | |
Next Step | |
Status | Approved on 08/13/2019 |
Effective Dates |
09/01/2019
Section 23N 02/11/2022
All remaining sections |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
08/13/2019 | BOARD | Approved | |
07/24/2019 | TAC | Recommended for Approval | Board for consideration |
05/22/2019 | TAC | Deferred/Tabled | TAC for consideration |
05/09/2019 | PRS | Recommended for Approval | TAC for consideration |
04/11/2019 | PRS | Recommended for Approval | PRS for Impact Analysis review |
01/17/2019 | PRS | Deferred/Tabled | PRS for consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
08/13/2019 | BOARD | To approve NPRR917 as recommended by TAC in the 7/24/19 TAC Report | Passed |
07/24/2019 | TAC | To recommend approval of NPRR917 as recommended by PRS in the 5/9/19 PRS Report as amended by the 7/17/19 LCRA comments as revised by TAC | Passed |
05/22/2019 | TAC | To table NPRR917 | Passed |
05/09/2019 | PRS | To endorse and forward to TAC the 4/11/19 PRS Report as amended by the 5/8/19 ERCOT Steel Mills comments as revised by PRS and the Impact Analysis for NPRR917 with an effective date of July 1, 2019 for Section 23, Form N, and a recommended priority of 2019 and rank of 2700 | Passed |
04/11/2019 | PRS | To recommend approval of NPRR917 as amended by the 4/4/19 ERCOT comments | Passed |
01/17/2019 | PRS | To table NPRR917 and refer the issue to ROS and WMS | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Jan 2, 2019 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 6.3.2, 6.6.3.2, 6.6.3.9 (new), 6.6.10, 9.5.3, 9.19.1, 10.3.2.3, 16.11.4.3.2, and 23N (new) |
Description: | This Nodal Protocol Revision Request (NPRR) implements nodal energy pricing, instead of the current Load Zone energy pricing, for Settlement Only Distribution Generators (SODGs) and Settlement Only Transmission Generators (SOTGs). For an SODG, the energy price used as the basis for the 15-minute Real-Time price calculation is the time-weighted price at the Electrical Bus associated with the mapped Load of the SODG in the Network Operations Model. For an SOTG, the energy price used as the basis for the 15-minute Real-Time price calculation is the time-weighted price at the Electrical Bus as determined by ERCOT in review of the meter location of the SOTG in the Network Operations Model. This NPRR also allows existing SODGs and SOTGs to apply to ERCOT to continue to receive Load Zone energy pricing until such time as they proactively opt in for nodal pricing, or January 1, 2030, whichever is earlier. |
Reason: | Addresses current operational issues. Meets Strategic goals. Market efficiencies / enhancements. |