OBDRR007
Summary
Title | Revisions to the ORDC Methodology to Include Photo-Voltaic Generation Resources (PVGRs) |
---|---|
Next Group | |
Next Step | |
Status | Approved on 12/11/2018 |
Effective Dates |
10/18/2019
|
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
12/11/2018 | BOARD | Approved | |
11/29/2018 | TAC | Recommended for Approval | Board for consideration |
09/26/2018 | TAC | Deferred/Tabled | TAC for consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
12/11/2018 | BOARD | To approve OBDRR007 as recommended by TAC in the 11/29/18 TAC Report | Passed |
11/29/2018 | TAC | To recommend approval of OBDRR007 as submitted and the associated Impact Analysis with a recommended priority of 2019 and rank of 2570 | Passed |
09/26/2018 | TAC | To table OBDRR007 | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Aug 1, 2018 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | Methodology for Implementing Operating Reserve Demand Curve (ORDC) to Calculate Real-Time Reserve Price Adder |
Description: | Since it was implemented in June 2014, the Operating Reserve Demand Curve (ORDC) methodology specifically excludes curtailed Photo-Voltaic Generation Resources (PVGRs) in the determination of the ORDC price adders. Since that time, substantial MWs of PVGRs have been installed in ERCOT, a considerable amount of which is being curtailed on a regular basis. This Other Binding Document Revision Request (OBDRR) changes the methodology to consider the additional capacity. |
Reason: | Addresses current operational issues |