Title Related to NPRR1085, Ensuring Continuous Validity of Physical Responsive Capability (PRC) and Dispatch through Timely Changes to Resource Telemetry and Current Operating Plans (COPs)
Next Group
Next Step
Status Approved on 05/11/2023

Action

Date Gov Body Action Taken Next Steps
05/11/2023 PUCT Approved
04/18/2023 BOARD Recommended for Approval Revision Request Consideration
03/21/2023 TAC Recommended for Approval Revision Request Consideration

Voting Record

Date Gov Body Motion Result
05/11/2023 PUCT to approve OBDRR044 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Rules Adopted by the Independent Organization Passed
04/18/2023 BOARD to recommend approval of OBDRR044 as recommended by TAC in the 3/21/23 TAC Report Passed
03/21/2023 TAC to recommend approval of OBDRR044 as submitted and the 2/14/23 Impact Analysis Passed

Background

Status: Approved
Date Posted: Feb 14, 2023
Sponsor: ERCOT
Urgent: No
Sections: Methodology for Implementing Operating Reserve Demand Curve (ORDC) to Calculate Real-Time Reserve Price Adder
Description: This Other Binding Revision Request (OBDRR) aligns the ORDC pricing with the Protocol revisions of NPRR1085 related to the ONHOLD status treatment of Resources.
Reason: Addresses current operational issues