MIS LOG IN

OGRR211

Summary

Title Deletion of References to Back-to-Back Import Capacity
Next Group
Next Step
Status Approved on 09/04/2008
Effective Dates
10/01/2008

Action

Date Gov Body Action Taken Next Steps
09/04/2008 TAC Approved
08/14/2008 ROS Recommended for Approval TAC review of OGRR211.
07/16/2008 OWG Recommended for Approval ROS review of OGRR211.
06/18/2008 OWG Recommended for Approval OWG Impact Analysis review

Voting Record

Date Gov Body Motion Result
09/04/2008 TAC To approve OGRR211 as recommended by ROS. Passed
08/14/2008 ROS To recommend approval of OGRR211 as recommended by OWG. Passed
07/16/2008 OWG Consensus to forward the OWG Recommendation Report and the Impact Analysis for OGRR211 to the ROS for consideration. Passed
06/18/2008 OWG Consensus to recommend approval of OGRR211 as submitted. Passed

Background

Status: Approved
Date Posted: May 22, 2008
Sponsor: ERCOT
Urgent: No
Sections: 4.5.3.3
Description: This OGRR deletes obsolete references to Back-to-Back (BtB) import capacity from the list of tasks ERCOT is responsible for under Emergency Electric Curtailment Plan (EECP) Step 1. It also replaces references to a "unit" in the EECP Steps with the defined term "Resource," and makes minor language corrections consistent with previous revisions to the ERCOT Protocols made pursuant to PRR726, DC Tie Scheduling Clarifications, which became effective on October 1, 2007.
Reason: To align the Operating Guides with the ERCOT Protocols by revising and deleting language previously removed from or revised in Protocol Section 5.6.7, EECP Steps, through PRR726.

Key Documents

Related Content