MIS LOG IN

OGRR225

Summary

Title Quick Start Units Qualification Ramp Period
Next Group
Next Step
Status Approved on 10/01/2009

Action

Date Gov Body Action Taken Next Steps
10/01/2009 TAC Approved
09/10/2009 ROS Recommended for Approval TAC consideration of OGRR225
08/19/2009 OWG Recommended for Approval ROS consideration of OGRR225
06/17/2009 OWG Recommended for Approval OWG Impact Analysis review

Voting Record

Date Gov Body Motion Result
10/01/2009 TAC To approve OGRR225 as recommended by ROS in the 9/10/09 ROS Recommendation Report and with a revised implementation date of "upon system implementation." Passed
09/10/2009 ROS To recommend approval of OGRR225 as recommended by OWG in the 8/19/09 OWG Recommendation Report. Passed
08/19/2009 OWG Consensus to endorse and forward the OWG Recommendation Report and Impact Analysis for OGRR225 to ROS. Passed
06/17/2009 OWG Consensus to recommend approval of OGRR225 as submitted. Passed

Background

Status: Approved
Date Posted: Apr 24, 2009
Sponsor: QMWG on behalf of WMS
Urgent: No
Sections: 2.5.5
Description: This Operating Guide Revision Request (OGRR) changes the Balancing Energy ramp period used for qualification of Quick Start Units to fourteen (14) minutes to align with PRR803, Revised Implementation Approach for PRR601.
Reason: This revision will allow more capacity from Quick Start Units to be offered into Balancing Energy Service.

Key Documents

Related Content