OGRR237
Summary
Title | Clarify the WGR Voltage Ride-Through Requirement |
---|---|
Next Group | |
Next Step | |
Status | Approved on 12/03/2009 |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
12/03/2009 | TAC | Approved | |
11/12/2009 | ROS | Recommended for Approval | TAC Consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
12/03/2009 | TAC | To approve OGRR237 as recommended by ROS in the 11/12/09 ROS Recommendation Report and as revised by TAC | Passed |
11/12/2009 | ROS | To recommend approval of OGRR237 as amended by the 11/12/09 Wind Coalition comments and as revised by ROS | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Oct 30, 2009 |
Sponsor: | ERCOT |
Urgent: | Yes |
Sections: | 3.1.4.6.1 |
Description: | This Operating Guide Revision Request (OGRR) clarifies that the VRT clearing-time requirement for relevant WGRs is nine (9) cycles unless a site-specific requirement is documented in conjunction with the SGIAs. These revisions clarify the existing requirements; they do not change the VRT requirement. |
Reason: | These revisions clarify the existing requirements; they do not change the VRT requirement. |
Key Documents
Oct 30, 2009 - doc - 235.5 KB
Oct 30, 2009 - doc - 67 KB
Oct 29, 2009 - doc - 43 KB
Nov 4, 2009 - xls - 93 KB
Nov 9, 2009 - doc - 45.5 KB
Nov 12, 2009 - doc - 43.5 KB
Nov 16, 2009 - doc - 89.5 KB
Dec 7, 2009 - doc - 91.5 KB