MIS LOG IN

PGRR004

Summary

Title Synchronization with NPRR291, Reduce the Comment Period for NPRRs and SCRs
Next Group
Next Step
Status Approved on 05/17/2011
Effective Dates
06/01/2011

Action

Date Gov Body Action Taken Next Steps
05/17/2011 BOARD Approved
04/07/2011 TAC Recommended for Approval ERCOT Board Consideration
03/10/2011 ROS Recommended for Approval TAC Consideration
02/25/2011 PLWG Recommended for Approval ROS Consideration
01/21/2011 PLWG Recommended for Approval PLWG IA Review

Voting Record

Date Gov Body Motion Result
05/17/2011 BOARD To approve PGRR004 as recommended by TAC in the 4/7/11 TAC Report. Passed
04/07/2011 TAC To recommend approval of PGRR004 as recommended by ROS in the 3/10/11 ROS Report. Passed
03/10/2011 ROS To recommend approval of PGRR004 as recommended by the PLWG in the 2/25/11 PLWG Report Passed
02/25/2011 PLWG Consensus to endorse and forward the 1/21/11 PLWG Report and Impact Analysis for PGRR004 to ROS
01/21/2011 PLWG Consensus to recommend approval of PGRR004 as submitted

Background

Status: Approved
Date Posted: Dec 27, 2010
Sponsor: ERCOT
Urgent: No
Sections: 2.4.3
Description: This Planning Guide Revision Request (PGRR) reduces the comment period for PGRRs from 21 days to 14 days and removes the requirement for the comment period to end at least three Business Days prior to the next regularly scheduled Planning Working Group (PLWG) meeting.
Reason: As a result of the Technical Advisory Committee (TAC) structural and process review, TAC requested ERCOT staff to draft an NPRR to reduce the comment period for NPRRs to 14 days. Since PGRRs have a similar initial comment period, proposed revisions to Planning Guide revision process are included in this PGRR to align with the Nodal Protocol revision process.

Key Documents

Related Content