Consensus to recommend approval of PGRR008 as revised by the PLWG
Background
Status:
Approved
Date Posted:
Apr 14, 2011
Sponsor:
ERCOT
Urgent:
No
Sections:
2.1, 2.2, Section 5 (new)
Description:
This Planning Guide Revision Request (PGRR) adds new Section 4, Generation Resource Interconnection. The majority of the language contained in this PGRR comes from the existing ERCOT Generation Interconnection or Change Request Procedure.
Reason:
Certain responsibilities and requirements related to interconnection studies for new Generation Resources are directly related to transmission planning and are appropriate for inclusion in the Planning Guide. The Planning Guide is being developed as requested by the Reliability and Operations Subcommittee (ROS) and the Technical Advisory Committee (TAC).