PGRR039
Summary
Title | Generation Data for Resource Adequacy and Reliability Reporting |
---|---|
Next Group | |
Next Step | |
Status | Approved on 12/09/2014 |
Effective Dates |
01/01/2015
|
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
12/09/2014 | BOARD | Approved | |
11/20/2014 | TAC | Recommended for Approval | ERCOT Board for consideration. |
10/30/2014 | ROS | Recommended for Approval | TAC for consideration. |
10/06/2014 | ROS | Deferred/Tabled | ROS for consideration |
09/17/2014 | PLWG | Recommended for Approval | ROS for consideration. |
08/20/2014 | PLWG | Recommended for Approval | PLWG for IA review. |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
12/09/2014 | BOARD | To approve PGRR039 as recommended by TAC in the 11/20/14 TAC Report. | Passed |
11/20/2014 | TAC | To recommend approval of PGRR039 as recommended by ROS in the 10/30/14 ROS Report. | Passed |
10/30/2014 | ROS | To recommend approval of PGRR039 as recommended by PLWG in the 9/17/14 PLWG Report. | Passed |
10/06/2014 | ROS | To table PGRR039 for one month. | Passed |
09/17/2014 | PLWG | To endorse and forward the 8/20/14 PLWG Report and the Impact Analysis for PGRR039 to ROS. | Passed |
08/20/2014 | PLWG | To recommend approval of PGRR039 as amended by the 8/12/14 Sharyland comments and as revised by PLWG. | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Jul 28, 2014 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 5.3.2, 5.5.1 |
Description: | This Planning Guide Revision Request (PGRR) proposes two changes to the Planning Guide. The first is new language in Section 5.3.2 that requires Interconnecting Entities (IEs) to provide certain information required for ERCOT’s Resource adequacy reports, Capacity, Demand and Reserves Report and the Seasonal Assessment of Resource Adequacy (SARA) Report, as well as for annual North American Electric Reliability Corporation (NERC) reliability assessment data requests. The second change, made to paragraph (2) of Section 5.5.1, ensures that ERCOT is a party to a decision by an IE and Transmission Service Provider (TSP) to execute a Standard Generation Interconnection Agreement (SGIA) before all interconnection studies have been completed and reviewed by the parties. |
Reason: | Addresses current operational issues and regulatory requirements. |
Key Documents
Jul 28, 2014 - doc - 102 KB
Jul 28, 2014 - doc - 55 KB
Aug 12, 2014 - doc - 60.5 KB
Aug 21, 2014 - doc - 108 KB
Sep 18, 2014 - doc - 99.5 KB
Oct 8, 2014 - doc - 113.5 KB
Nov 4, 2014 - doc - 110 KB
Nov 20, 2014 - doc - 112 KB
Dec 10, 2014 - doc - 113 KB