Title | Clarification of Water Supply Rights Attestation Obligation |
---|---|
Next Group | |
Next Step | |
Status | Approved on 06/09/2015 |
Effective Dates |
07/01/2015
|
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
06/09/2015 | BOARD | Approved | |
05/28/2015 | TAC | Recommended for Approval | Revision Request Consideration |
05/07/2015 | ROS | Recommended for Approval | Revision Request Consideration |
03/25/2015 | PLWG | Recommended for Approval | Revision Request Consideration |
01/21/2015 | PLWG | Deferred/Tabled | Impact Analysis Consideration |
12/17/2014 | PLWG | Recommended for Approval | PLWG for Impact Analysis review |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
06/09/2015 | BOARD | To approve PGRR040 as recommended by TAC in the 5/28/15 TAC Report. | Passed |
05/28/2015 | TAC | To recommend approval of PGRR040 as recommended by ROS in the 5/7/15 ROS Report. | Passed |
05/07/2015 | ROS | To recommend approval of PGRR040 as recommended by PLWG in the 3/25/15 PLWG Report. There was one abstention from the Independent Generator Market Segment. | Passed |
03/25/2015 | PLWG | To endorse and forward to ROS the 1/21/15 PLWG Report as revised by PLWG and the Impact Analysis for PGRR040. | Passed |
01/21/2015 | PLWG | To table PGRR040. | Passed |
12/17/2014 | PLWG | To recommend approval of PGRR040 as submitted. | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Dec 2, 2014 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 5.5.4, 6.9, 8 Attachment B |
Description: | This Planning Guide Revision Request (PGRR) provides further clarification about when a proposed Generation Resource will be included in ERCOT’s planning models. First, this PGRR simplifies Section 6.9 by providing that an Interconnecting Entity (IE) meets the requirement to attest to sufficient water supplies by completing and submitting the Declaration of Adequate Water Supply Rights in Planning Guide Section 8, Attachment B. Second, this PGRR modifies Attachment B to allow an IE to attest that its Generation Resource does not require water supplies to generate electricity. Third, this PGRR provides that any IE proposing a Generation Resource powered by wind or photovoltaic solar technology is not required to submit proof of an air permit or an attestation of water supply rights as a condition for ERCOT’s inclusion of a proposed Generation Resource in the base cases. This PGRR also makes corresponding modifications to Section 5.5.4, Notification to ERCOT Concerning Certain Project Developments, and clarifies that all data required by the Resource Registration Glossary must be submitted as a condition for inclusion in the planning models. |
Reason: | Addresses current operational issues. |
Key Documents
Dec 2, 2014 - doc - 102.5 KB
Dec 2, 2014 - doc - 54.5 KB
Dec 19, 2014 - doc - 115 KB
Jan 23, 2015 - doc - 115.5 KB
Mar 27, 2015 - doc - 121 KB
May 12, 2015 - doc - 122 KB
May 29, 2015 - doc - 127.5 KB
Jun 11, 2015 - doc - 128.5 KB