Summary

Title Revise and Add Requirements for NERC TPL-001-4 Standard
Next Group
Next Step
Status Approved on 04/14/2015
Effective Dates
05/01/2015

Action

Date Gov Body Action Taken Next Steps
04/14/2015 BOARD Approved
03/26/2015 TAC Recommended for Approval Revision Request Consideration
03/12/2015 ROS Recommended for Approval Revision Request Consideration
02/16/2015 PLWG Recommended for Approval Revision Request Consideration
01/21/2015 PLWG Recommended for Approval Impact Analysis Consideration
12/17/2014 PLWG Recommended for Approval PLWG for Impact Analysis review.

Voting Record

Date Gov Body Motion Result
04/14/2015 BOARD Approved PGRR041 as recommended by TAC in the 3/26/15 TAC Report. Passed
03/26/2015 TAC To recommend approval of PGRR041 as recommended by ROS in the 3/12/15 ROS Report. Passed
03/12/2015 ROS To recommend approval of PGRR041 as recommended by PLWG in the 2/16/15 PLWG Report and as amended by the 3/3/15 ERCOT comments. Passed
02/16/2015 PLWG To endorse and forward to ROS the 1/21/15 PLWG Report as revised by PLWG and the revised Impact Analysis for PGRR041 Passed
01/21/2015 PLWG To endorse the 12/17/14 PLWG Report as amended by the 1/20/15 Oncor comments and as revised by PLWG, and to request ERCOT bring a revised Impact Analysis back to PLWG for review. Passed
12/17/2014 PLWG To recommend approval of PGRR041 as revised by PLWG. Passed

Background

Status: Approved
Date Posted: Dec 2, 2014
Sponsor: ERCOT
Urgent: No
Sections: 2.1, 3.1.3.1, 4.1, 4.1.1.2, 4.1.1.3, 4.1.1.4, 4.1.1.5, 4.1.1.6, 4.1.2, 4.1.2.1, 4.1.2.2, 6.10
Description: This Planning Guide Revision Request (PGRR) revises and adds requirements to satisfy the North American Electric Reliability Corporation (NERC) Standard TPL-001-4, Transmission Planning Performance Requirement.
Reason: Regulatory requirements