PGRR045
Summary
Title | Alignment with NPRR705, Provides Consistency for References to the End Date of the Generation Interconnection Process |
---|---|
Next Group | |
Next Step | |
Status | Approved on 12/08/2015 |
Effective Dates |
01/01/2016
|
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
12/08/2015 | BOARD | Approved | |
11/19/2015 | TAC | Recommended for Approval | Revision Request Consideration |
11/10/2015 | ROS | Recommended for Approval | Revision Request Consideration |
10/19/2015 | PLWG | Recommended for Approval | Revision Request Consideration |
09/15/2015 | PLWG | Recommended for Approval | Impact Analysis Consideration |
06/22/2015 | PLWG | Deferred/Tabled | Language Consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
12/08/2015 | BOARD | Approved PGRR045 as recommended by TAC in the 11/19/15 TAC Report. | Passed |
11/19/2015 | TAC | To recommend approval of PGRR045 as recommended by ROS in the 11/10/15 ROS Report. | Passed |
11/10/2015 | ROS | To recommend approval of PGRR045 as recommended by PLWG in the 10/19/15 PLWG Report. | Passed |
10/19/2015 | PLWG | To endorse and forward to ROS the 9/15/15 PLWG Report and Impact Analysis for PGRR045. | Passed |
09/15/2015 | PLWG | To recommend approval of PGRR045 as submitted. | Passed |
06/22/2015 | PLWG | To table PGRR045. | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | May 20, 2015 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 5.3.2, 5.4.3, 5.4.5, 5.4.10, 5.7.1, 5.7.2 |
Description: | In the Resource Interconnection Handbook, the term “commercial operations” has a different meaning to Resource Entities and financial institutions involved in construction and financing of Generation Resources than it does in the context of performance testing by ERCOT for new Generation Resources. This Planning Guide Revision Request (PGRR) aligns the Planning Guides with NPRR705 by replacing various terms used to refer to the date on which Generation Resources complete the Resource interconnection process with the proposed defined terms “Commercial Operations Date” and “Resource Commissioning Date” to provide consistency for references to the end of the generation interconnection process. |
Reason: | Administrative |
Key Documents
Jun 11, 2015 - doc - 112.5 KB
May 20, 2015 - doc - 55.5 KB
Jun 23, 2015 - doc - 104.5 KB
Sep 16, 2015 - doc - 100 KB
Oct 20, 2015 - doc - 100.5 KB
Nov 10, 2015 - xls - 130 KB
Nov 11, 2015 - doc - 55.5 KB
Nov 12, 2015 - doc - 119 KB
Nov 19, 2015 - doc - 122.5 KB
Dec 8, 2015 - doc - 123.5 KB