to approve PGRR095 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization
to recommend approval of PGRR095 as recommended by ROS in the 2/7/22 ROS Report; and for the minimum deliverability criteria, a minimum percentage of capacity of 100% to serve expected coincident peak Load.
to table PGRR095 and refer the issue to the Planning Working Group (PLWG
Passed
Background
Status:
Approved
Date Posted:
Aug 26, 2021
Sponsor:
ERCOT
Urgent:
No
Sections:
4.1.1.7 (new)
Description:
This Planning Guide Revision Request (PGRR) establishes minimum deliverability criteria for Resources that are located within the ERCOT System and whose output is primarily within ERCOT’s control, through Dispatch Instructions, over the entire real power capability range of each Resource.
Reason:
Addresses current operational issues; Meets Strategic goals (tied to the ERCOT Strategic Plan or directed by the ERCOT Board).