to approve PGRR096 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization
to table PGRR096 and refer the issue to the Planning Working Group (PLWG) and the Steady State Working Group (SSWG)
Passed
Background
Status:
Approved
Date Posted:
Sep 22, 2021
Sponsor:
ERCOT
Urgent:
No
Sections:
6.1
Description:
This Planning Guide Revision Request (PGRR) establishes requirements for the consistent representation of Distribution Generation Resources (DGRs), Distribution Energy Storage Resources (DESRs), Settlement Only Distribution Generators (SODGs), and unregistered Distributed Generation (DG) in steady-state base cases.