Summary
Title | Revise GIM Process to Ensure Compliance with the Lone Star Infrastructure Protection Act |
---|---|
Next Group | |
Next Step | |
Status | Approved on 03/31/2022 |
Effective Dates |
04/01/2022
|
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
03/31/2022 | PUCT | Approved | |
03/07/2022 | BOARD | Recommended for Approval | Revision Request Consideration |
01/31/2022 | TAC | Recommended for Approval | Revision Request Consideration |
01/06/2022 | ROS | Recommended for Approval | Revision Request Consideration |
12/02/2021 | ROS | Recommended for Approval | Impact Analysis Consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
03/31/2022 | PUCT | to approve PGRR099 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization | Passed |
03/07/2022 | BOARD | to recommend approval of PGRR099 as recommended by TAC in the 1/31/22 TAC Report. | Passed |
01/31/2022 | TAC | to recommend approval of PGRR099 as recommended by ROS in the 1/6/22 ROS Report | Passed |
01/06/2022 | ROS | to endorse and forward to TAC the 12/2/21 ROS Report, as amended by the 12/17/21 ERCOT comments, and the Impact Analysis for PGRR099 with a recommended priority of 2022 and rank of 310 | Passed |
12/02/2021 | ROS | to recommend approval of PGRR099 as amended by the 11/29/21 Joint TSPs comments | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Nov 17, 2021 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 5.1, 5.2.2, 5.2.5, and 8 Attachment D |
Description: | This Planning Guide Revision Request (PGRR) amends Section 5.2.2 by providing that an Entity will not be eligible to initiate or maintain a Generator Interconnection or Modification (GIM) if the Entity or any other owner of the project meets any of the company ownership (including affiliations) or headquarters criteria listed in the Lone Star Infrastructure Protection Act, Texas Business and Commerce Code, Sections 113.002(a)(2)(A)-(b)(2)(B) or 2274.0102(a)(2)(A)-(b)(2)(B), added by Act of June 18, 2021, 87th Leg. R.S., Ch. 975 (S.B. 2116). An Entity will also not be eligible to initiate or maintain a GIM if the real property to be utilized by or for the project is owned or controlled, in whole or in part, by an Entity that meets any of the above-mentioned criteria. Any Entity that seeks to initiate a GIM will be required to submit an attestation confirming that it does not meet the statutory criteria. If there are changes in the ownership or headquarters location of the Interconnecting Entity (IE), then the new IE will be required to submit an attestation confirming that, despite the changes, it does not meet the statutory criteria. Finally, an attestation form is added in Section 8, as Attachment D, Attestation Regarding Compliance with the Lone Star Infrastructure Protection Act. |
Reason: | Regulatory requirements |
Key Documents
Nov 17, 2021 - doc - 119 KB
Nov 17, 2021 - docx - 30.2 KB
Nov 29, 2021 - doc - 96.5 KB
Dec 7, 2021 - xls - 107 KB
Dec 7, 2021 - doc - 125 KB
Dec 17, 2021 - doc - 98.5 KB
Jan 11, 2022 - xls - 138.5 KB
Jan 11, 2022 - doc - 127 KB
Jan 14, 2022 - xls - 145.5 KB
Jan 14, 2022 - doc - 84 KB
Feb 3, 2022 - xls - 141.5 KB
Feb 3, 2022 - doc - 133 KB
Mar 10, 2022 - doc - 163.5 KB
Apr 1, 2022 - doc - 137.5 KB