MIS LOG IN

PGRR103

Summary

Title Establish Time Limit for Generator Commissioning Following Approval to Synchronize
Next Group
Next Step
Status Approved on 10/12/2023

Action

Date Gov Body Action Taken Next Steps
10/12/2023 PUCT Approved
08/31/2023 BOARD Recommended for Approval Revision Request Consideration
06/27/2023 TAC Recommended for Approval Revision Request Consideration
06/08/2023 ROS Recommended for Approval Revision Request Consideration
05/04/2023 ROS Deferred/Tabled Impact Analysis Consideration
04/06/2023 ROS Recommended for Approval Impact Analysis Consideration
01/05/2023 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
10/12/2023 PUCT to approve PGRR103 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Rules Adopted by the Independent Organization Passed
08/31/2023 BOARD to recommend approval of PGRR103 as recommended by TAC in the 6/27/23 TAC Report Passed
06/27/2023 TAC to recommend approval of PGRR103 as recommended by ROS in the 6/8/23 ROS Report Passed
06/08/2023 ROS to endorse and forward to TAC the 5/4/23 ROS Report and 6/6/23 Revised Impact Analysis for PGRR103 with a recommended priority of 2024 and rank of 4020 Passed
05/04/2023 ROS to table PGRR103 Passed
04/06/2023 ROS to recommend approval of PGRR103 as amended by the 3/23/23 PLWG comments Passed
01/05/2023 ROS to table PGRR103 and refer the issue to the Operations Working Group (OWG) and Planning Working Group (PLWG) Passed

Background

Status: Approved
Date Posted: Dec 21, 2022
Sponsor: ERCOT
Urgent: No
Sections: 5.5
Description: This Planning Guide Revision Request (PGRR) requires an Interconnecting Entity to complete all conditions for commercial operation of a Generation Resource or Energy Storage Resource (ESR) within 180 days of receiving approval for Initial Synchronization from ERCOT.
Reason: Addresses current operational issues

Key Documents

Related Content