to approve PGRR103 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Rules Adopted by the Independent Organization
to endorse and forward to TAC the 5/4/23 ROS Report and 6/6/23 Revised Impact Analysis for PGRR103 with a recommended priority of 2024 and rank of 4020
to table PGRR103 and refer the issue to the Operations Working Group (OWG) and Planning Working Group (PLWG)
Passed
Background
Status:
Approved
Date Posted:
Dec 21, 2022
Sponsor:
ERCOT
Urgent:
No
Sections:
5.5
Description:
This Planning Guide Revision Request (PGRR) requires an Interconnecting Entity to complete all conditions for commercial operation of a Generation Resource or Energy Storage Resource (ESR) within 180 days of receiving approval for Initial Synchronization from ERCOT.