PGRR106

Summary

Title Clarify Projects Included in Transmission Project Information and Tracking (TPIT) Report
Next Group
Next Step
Status Approved on 09/26/2024

Action

Date Gov Body Action Taken Next Steps
09/26/2024 PUCT Approved
08/20/2024 BOARD Recommended for Approval Revision Request Consideration
06/24/2024 TAC Recommended for Approval Revision Request Consideration
06/06/2024 ROS Recommended for Approval Revision Request Consideration
05/02/2024 ROS Recommended for Approval Impact Analysis Consideration
05/04/2023 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
09/26/2024 PUCT to approve PGRR106 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization Passed
08/20/2024 BOARD to recommend approval of PGRR106 as recommended by TAC in the 6/24/24 TAC Report Passed
06/24/2024 TAC to recommend approval of PGRR106 as recommended by ROS in the 6/6/24 ROS Report Passed
06/06/2024 ROS to endorse and forward to TAC the 5/2/24 ROS Report and the 4/19/23 Impact Analysis for PGRR106 Passed
05/02/2024 ROS to recommended approval of PGRR106 as amended by the 12/12/23 ERCOT comments Passed
05/04/2023 ROS to table PGRR106 and refer the issue to the Steady State Working Group (SSWG). Passed

Background

Status: Approved
Date Posted: Apr 19, 2023
Sponsor: ERCOT
Urgent: No
Sections: 2.2, 6.4.1
Description: This Planning Guide Revision Request (PGRR) clarifies what transmission projects are included in the Transmission Project Information and Tracking (TPIT) report.
Reason: General system and/or process improvement(s)