PGRR110

Summary

Title Revision to Accommodate Steady-State Node-Breaker Modeling
Next Group
Next Step
Status Approved on 02/01/2024

Action

Date Gov Body Action Taken Next Steps
02/01/2024 PUCT Approved
12/19/2023 BOARD Recommended for Approval Revision Request Consideration
10/24/2023 TAC Recommended for Approval Revision Request Consideration
10/05/2023 ROS Recommended for Approval Revision Request Consideration
09/07/2023 ROS Recommended for Approval Impact Analysis Consideration
08/03/2023 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
02/01/2024 PUCT to approve PGRR110 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization Passed
12/19/2023 BOARD to recommend approval of PGRR110 as recommended by TAC in the 10/24/23 TAC Report Passed
10/24/2023 TAC to recommend approval of PGRR110 as recommended by ROS in the 10/5/23 ROS Report Passed
10/05/2023 ROS to endorse and forward to TAC the 9/7/23 ROS Report and 7/19/23 Impact Analysis for PGRR110 Passed
09/07/2023 ROS to recommend approval of PGRR110 as submitted Passed
08/03/2023 ROS to table PGRR110 and refer the issue to the Steady State Working Group (SSWG) Passed

Background

Status: Approved
Date Posted: Jul 19, 2023
Sponsor: ERCOT
Urgent: No
Sections: 6.1
Description: This Planning Guide Revision Request (PGRR) removes paragraph (2)(a) of Section 6.1 to accommodate the release of steady-state planning models in node-breaker format pursuant to System Change Request (SCR) 789, Update NMMS Topology Processor to PSSE 34 Capability.
Reason: Market efficiencies or enhancements