PGRR113

Summary

Title Related to NPRR1198, Congestion Mitigation Using Topology Reconfigurations
Next Group
Next Step
Status Approved on 07/25/2024

Action

Date Gov Body Action Taken Next Steps
07/25/2024 PUCT Approved
06/18/2024 BOARD Recommended for Approval Revision Request Consideration
05/22/2024 TAC Recommended for Approval Revision Request Consideration
05/02/2024 ROS Recommended for Approval Revision Request Consideration
04/04/2024 ROS Recommended for Approval Impact Analysis Consideration
12/07/2023 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
07/25/2024 PUCT to approve PGRR113 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization Passed
06/18/2024 BOARD to recommend approval of PGRR113 as recommended by TAC in the 5/22/24 TAC Report Passed
05/22/2024 TAC to recommend approval of PGRR113 as recommended by ROS in the 5/2/24 ROS Report Passed
05/02/2024 ROS to endorse and forward to TAC the 4/4/24 ROS Report and the 4/30/24 Revised Impact Analysis for PGRR113 Passed
04/04/2024 ROS to recommend approval of PGRR113 as submitted Passed
12/07/2023 ROS to table PGRR113 and refer the issue to the Planning Working Group (PLWG) Passed

Background

Status: Approved
Date Posted: Nov 14, 2023
Sponsor: ERCOT
Urgent: No
Sections: 3.1.4.1.1 and 4.1.1.2
Description: This Planning Guide Revision Request (PGRR) revises the Planning Guide to provide that ERCOT will first consider transmission needs without Constraint Management Plan (CMP) actions in its Regional Transmission Plan studies, and will then only model a CMP in the Regional Transmission Plan in certain limited circumstances. A CMP will not be planned to resolve a planning criteria performance deficiency unless it is expected that system conditions will change such that the CMP will no longer be needed within the next five years.
Reason: Strategic Plan Objective 2