Summary

Title Addition of Resiliency Assessment and Criteria to Reflect PUCT Rule Changes
Next Group TAC
Next Step Revision Request Consideration
Status Pending

Action

Date Gov Body Action Taken Next Steps
12/05/2024 ROS Recommended for Approval Revision Request Consideration
11/07/2024 ROS Recommended for Approval Impact Analysis Consideration
08/01/2024 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
12/05/2024 ROS to endorse and forward to TAC the 11/7/24 ROS Report and the 7/17/24 Impact Analysis for PGRR117 Passed
11/07/2024 ROS to recommend approval of PGRR117 as amended by the 10/11/24 ERCOT comments Passed
08/01/2024 ROS to table PGRR117 and refer the issue to the Planning Working Group (PLWG) Passed

Background

Status: Pending
Date Posted: Jul 17, 2024
Sponsor: ERCOT
Urgent: No
Sections: 2.2; 3.1.1.6 (new); 4.1; 4.1.2 (new)
Description: This Planning Guide Revision Request (PGRR) revises the Planning Guide to reflect the Public Utility Commission of Texas’ (PUCT’s) rulemaking addition of subsection (b)(3)(E) to 16 Texas Administrative Code (TAC) § 25.101, Certification Criteria, which requires ERCOT to conduct a biennial assessment of the ERCOT power grid’s reliability and resiliency in extreme weather scenarios and permits ERCOT to recommend transmission projects to address resiliency issues identified in the assessment. ERCOT intends to perform the biennial assessment in parallel with the Regional Transmission Plan (RTP) process.
Reason: Regulatory requirements

Key Documents