PGRR120
Summary
Title | SSO Prevention for Generator Interconnection |
---|---|
Next Group | ROS |
Next Step | ROS for consideration |
Status | Pending |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
11/07/2024 | ROS | Deferred/Tabled | ROS for consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
11/07/2024 | ROS | To table PGRR120 and refer the issue to the Planning Working Group (PLWG) and Dynamics Working Group (DWG) | Passed |
Background
Status: | Pending |
---|---|
Date Posted: | Oct 14, 2024 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 5.2.10 (new) |
Description: | This Planning Guide Revision Request (PGRR) prevents generators from interconnecting to the ERCOT Transmission Grid if the generator would be radial to a series capacitor under N-1 conditions. |
Reason: | Strategic Plan Objective 1 |
Key Documents
Oct 14, 2024 - docx - 44.7 KB
Oct 14, 2024 - docx - 31.2 KB
Nov 11, 2024 - xls - 137.5 KB
Nov 11, 2024 - docx - 46 KB
Dec 17, 2024 - docx - 35.9 KB
Jan 28, 2025 - docx - 31.4 KB
Feb 7, 2025 - docx - 29.5 KB
Feb 13, 2025 - docx - 29.5 KB