To table PGRR120 and refer the issue to the Planning Working Group (PLWG) and Dynamics Working Group (DWG)
Passed
Background
Status:
Pending
Date Posted:
Oct 14, 2024
Sponsor:
ERCOT
Urgent:
No
Sections:
5.2.10 (new)
Description:
This Planning Guide Revision Request (PGRR) prevents generators from interconnecting to the ERCOT Transmission Grid if the generator would be radial to a series capacitor under N-1 conditions.