Curtailment Prioritization for Wind Generators Introduces the concept of using in-service date to determine curtailment priority in situations where only wind generators are needed to resolve local congestion
Next Group
Next Step
Status
Withdrawn
Action
Date
Gov Body
Action Taken
Next Steps
No updates have been made to this issue.
Voting Record
Date
Gov Body
Motion
Result
No updates have been made to this issue.
Background
Status:
Withdrawn
Date Posted:
Apr 30, 2004
Sponsor:
FPL Energy
Urgent:
No
Sections:
7.4.2, 7.8.8
Description:
Requires new WPGRs locating in the McCamey area to install Special Protection Schemes to limit their output.