MIS LOG IN

PRR573

Summary

Title Mothballed Generation Resource Definition and Time to Service Updates
Next Group
Next Step
Status Approved

Action

Date Gov Body Action Taken Next Steps
No updates have been made to this issue.

Voting Record

Date Gov Body Motion Result
No updates have been made to this issue.

Background

Status: Approved
Date Posted: Feb 9, 2005
Sponsor: Austin Energy
Urgent: Yes
Sections: 1.3.1.1, 2.1, 6.5.9.3
Description: This defines mothballed units and requires the responsible Generation Entity to report to ERCOT, twice annually, the lead time required to reliably return the unit to service. The Generation Entity would be required to document its claim to ERCOTs satisfaction. Time to service updates and supporting documentation would be considered Protected Information.
Reason:

Key Documents

Related Content