PRR622

Summary

Title Calculation of Marginal Heat Rate for Resources Receiving OOME Up Instructions
Next Group
Next Step
Status Approved on 12/13/2005
Effective Dates
01/01/2006

Action

Date Gov Body Action Taken Next Steps
12/13/2005 BOARD Approved Effective 1/1/06

Voting Record

Date Gov Body Motion Result
12/13/2005 BOARD Approve PRR622 as recommended by TAC Passed

Background

Status: Approved
Date Posted: Aug 25, 2005
Sponsor: ERCOT
Urgent: No
Sections: 6.8.2.3
Description: During the process of drafting language for PRR 540 (OOM Cost Recovery Process Clarification) a sentence was inadvertently left in the Protocols which is not consistent with the intent or scope of other Sections describing how to calculate a Generation Resource Marginal Heat Rate. In particular, under Section 6.8.2.3 (4)(b)(ii), the Protocols state; ERCOT will use the heat rate of the Resource at the deployed level. This is not consistent with the rest of the subparagraph describing Marginal Heat Rates and should be removed.