Recommend approval of PRR627 as revised by the PRR627 Task Force and Centerpoint
Passed
Background
Status:
Approved
Date Posted:
Aug 26, 2005
Sponsor:
TXU Wholesale
Urgent:
No
Sections:
6.5.9.4 (new), 6.5.9.5 (new), 6.5.9.6 (new), 22F
Description:
Establishes reporting requirements for TDSPs responsible for construction of transmission system upgrades associated with an RMR and/or MRA exit strategy. Also provides ERCOT with additional flexibility to deal with potential delays in the completion of transmission system upgrades associated with an RMR and/or MRA exit strategy. ERCOT will be able to extend an RMR and/or MRA contract for limited time periods as necessary to allow for planned transmission system upgrades to be completed. ERCOT will also be able to require reporting of project status from the responsible TDSP.