On 01/19/06, PRS voted to recommend approval of PRR630 as modified by ERCOT comments and PRS, and endorse the PRS Recommendation Report and Impact Analysis with three abstentions from the Consumer (2) and Independent Power Marketer (1) segments. All market segments were present.
On 12/16/2005 PRS voted to recommended approval of PRR630 as modified by Centerpoint's comments. The motion passed with two opposing votes from the Consumers and Independent REPs and two abstentions from the Investor Owned Utilities and the Independent Generators. All market segments were present.
Passed
Background
Status:
Approved
Date Posted:
Aug 26, 2005
Sponsor:
TXU Wholesale
Urgent:
No
Sections:
2.1, 5.2.1, 5.2.2
Description:
Adds a requirement for private use networks (i.e., those networks that are connected to the ERCOT System that may include both generation and Load behind the meter) to maintain and report appropriate watt/VAR metering at each substation identical to the requirements of Distribution Service Providers (DSPs) and reporting of the addition or deletion of Load points.