Recommendation for approval as recommended by WMS comments.
Passed
Background
Status:
Approved
Date Posted:
Apr 10, 2006
Sponsor:
WMS Frequency TF
Urgent:
Yes
Sections:
6.10.6
Description:
Clarifies current language exempting the intervals following a Forced Outage from the Schedule Control Error compliance measure and adds additional exemptions to address infeasible portfolio instructions, Responsive Reserve Service ramping, unit testing, and the scheduling of Uncontrollable Renewable Resources.
Reason:
A Schedule Control Error performance measure stringent enough to meaningfully contribute to satisfactory system frequency control and efficient procurement and deployment of Regulation Service cannot, in most instances, be met by QSEs experiencing one or more of the exempted events addressed in this proposed revision.