Refer PRR664 to ROS and place the notification of the Ancillary Service (AS) re-qualification testing issue on the June TAC agenda, so that TAC may request that the ERCOT Board grant a 60-day delay in the 07/31/06 AS re-qualification testing deadline for QSEs that were qualified at market open.
Passed
Background
Status:
Approved
Date Posted:
Apr 21, 2006
Sponsor:
PDCWG
Urgent:
No
Sections:
6.10.5.5, Non-Spinning Reserve Services Performance Monitoring Criteria; 6.10.3, Ancillary Services Qualification Criteria and Portfolio Test Methods
Description:
Revise the Non-Spinning Reserve Service (NSRS) Performance Monitoring Criteria.
Reason:
To accurately reflect compliant performance by Qualified Scheduling Entities (QSEs).