Title Distribution Loss Factor Calculations
Next Group
Next Step
Status Approved on 09/19/2006

Voting Record

Date Gov Body Motion Result
09/19/2006 BOARD The ERCOT Board unanimously approved PRR668 as recommended by TAC. Passed
08/03/2006 TAC Recommend approval of PRR668, including rank and priority as recommended by PRS. Passed
07/20/2006 PRS Recommendation to assign a rank of 32.6 and priority of 1.1 on the 2006 Project Prioritization List (PPL) and a priority of 2 (high rank) on the 2007 PPL. Passed
06/22/2006 PRS Recommend approval as revised by TXU Electric Delivery comments Passed

Background

Status: Approved
Date Posted: May 24, 2006
Sponsor: Unaccounted For Energy Task Force (UFETF)
Urgent: No
Sections: 13.3
Description: Modify the Settlement Interval Distribution Loss Factor (SILF) to better represent the non-linear relationship between the loss factor and Settlement Interval ERCOT System Load (SIEL).
Reason: The current Distribution Loss Factor (DLF) formula assumes a straight line relationship between DLF and ERCOT system load, which results in mis-estimation of distribution losses in settlement. The proposed formula is non-linear and will better represent distribution losses.