PRR674

Summary

Title Temporary Alteration of Settlement Equations Related to the RPRS Under Scheduled Charge
Next Group
Next Step
Status Approved on 09/19/2006

Action

Date Gov Body Action Taken Next Steps
09/19/2006 BOARD Approved Report the impact of PRR674 on the Balancing Energy market at the November, 2006, Board meeting.
09/07/2006 TAC Rejected
08/31/2006 PRS Rejected

Voting Record

Date Gov Body Motion Result
09/19/2006 BOARD The Board voted on a motion to grant CNE's appeal of the TAC decision and approve PRR674 as submitted, effective until the earlier of February 1, 2007 or the implementation of PRR676. The Board also directed ERCOT Staff to report the impacts of PRR674 on the Balancing Energy market to the Board in November, 2006. Passed
09/07/2006 TAC Reject appeal of Constellation NewEnergy of PRS decision. Passed
08/31/2006 PRS To reject. Passed

Background

Status: Approved
Date Posted: Jul 19, 2006
Sponsor: Constellation NewEnergy
Urgent: Yes
Sections: 6.9.2.1.1, 6.9.2.1.2
Description: This PRR temporarily alters the settlement equations for the RPRS Under Scheduled charge.
Reason: Current settlement of the RPRS Under Scheduled Charge is improper. This PRR temporarily alters the settlement, uplifting the cost of RPRS on a load ratio share, until issues relating to RPRS are corrected. Once a new PRR to address all of the issues brought up the board meeting is approved, this revision will no longer be needed.