PRR713

Summary

Title Resource Outage Notification
Next Group
Next Step
Status Approved on 09/18/2007
Effective Dates
10/01/2007

Action

Date Gov Body Action Taken Next Steps
09/18/2007 BOARD Approved
08/02/2007 TAC Recommended for Approval Board of Directors consideration of this PRR
07/19/2007 PRS Recommended for Approval TAC consideration of this PRR
06/21/2007 PRS Recommended for Approval PRS consideration of Impact Analysis
03/22/2007 PRS Deferred/Tabled PRS consideration

Voting Record

Date Gov Body Motion Result
09/18/2007 BOARD To approve this PRR as recommended by the TAC Passed
08/02/2007 TAC To recommend approval of PRR713 as recommended by PRS Passed
07/19/2007 PRS To forward the PRS Recommendation Report and IA to TAC. Passed
06/21/2007 PRS To recommend approval of PRR713 initial language Passed
03/22/2007 PRS Table Passed

Background

Status: Approved
Date Posted: Feb 21, 2007
Sponsor: ERCOT Staff
Urgent: No
Sections: 6.5.9, Reliability Must-Run Service; 6.5.9.1, Initiation and Approval of RMR Agreements; 6.5.9.3, Mothballed Generation Resource Time to Service Updates; 8.4, Acceptance of Proposed Planned Outages of Resources other than Reliability Resources; Section 22, Attachment I: Notification of Suspension of Operations; Section 22, Attachment F: Standard Form Reliability Must-Run Agreement; Section 22, Attachment K: Notification of Change of Generation Resource Designation (New)
Description: This PRR clarifies and further details the long-term outage notification submission process for resources.
Reason: To clarify and expand explanation options for long-term outages. This is necessary for ERCOT and Transmission and Distribution Service Provider (TDSP) modeling accuracy so that the transmission system can be planned and operated reliably.