6.5.9, Reliability Must-Run Service; 6.5.9.1, Initiation and Approval of RMR Agreements; 6.5.9.3, Mothballed Generation Resource Time to Service Updates; 8.4, Acceptance of Proposed Planned Outages of Resources other than Reliability Resources; Section 22, Attachment I: Notification of Suspension of Operations; Section 22, Attachment F: Standard Form Reliability Must-Run Agreement; Section 22, Attachment K: Notification of Change of Generation Resource Designation (New)
Description:
This PRR clarifies and further details the long-term outage notification submission process for resources.
Reason:
To clarify and expand explanation options for long-term outages. This is necessary for ERCOT and Transmission and Distribution Service Provider (TDSP) modeling accuracy so that the transmission system can be planned and operated reliably.