PRR723

Summary

Title Conform 5.6.6.1 EECP (formally titled "Emergency Interruptible Load Service Formula Correction")
Next Group
Next Step
Status Approved on 06/19/2007
Effective Dates
07/01/2007

Voting Record

Date Gov Body Motion Result
06/19/2007 BOARD Approve PRR723 as recommended by TAC. Passed
06/07/2007 TAC Recommend approval of PRR723 as recommended by PRS Passed
05/17/2007 PRS Recommend approval of PRR723 as modified by PRS. Passed

Background

Status: Approved
Date Posted: May 16, 2007
Sponsor: ERCOT
Urgent: Yes
Sections: 5.6.6.1
Description: This Protocol Revision Request (PRR) proposes technical corrections to the progression of the Steps during an EECP event in Protocol Section 5.6.6.1.
Reason: Correction to the Protocols to allow ERCOT to proceed to Step 4 when necessary during an EECP event to ensure system reliability.