PRR723
Summary
Title |
Conform 5.6.6.1 EECP (formally titled "Emergency Interruptible Load Service Formula Correction") |
Next Group |
|
Next Step |
|
Status |
Approved on 06/19/2007 |
Effective Dates |
|
Voting Record
Date |
Gov Body |
Motion |
Result |
06/19/2007
|
BOARD |
Approve PRR723 as recommended by TAC. |
Passed |
06/07/2007
|
TAC |
Recommend approval of PRR723 as recommended by PRS |
Passed |
05/17/2007
|
PRS |
Recommend approval of PRR723 as modified by PRS. |
Passed |
Background
Status: |
Approved |
Date Posted: |
May 16, 2007
|
Sponsor: |
ERCOT |
Urgent: |
Yes |
Sections: |
5.6.6.1 |
Description: |
This Protocol Revision Request (PRR) proposes technical corrections to the progression of the Steps during an EECP event in Protocol Section 5.6.6.1. |
Reason: |
Correction to the Protocols to allow ERCOT to proceed to Step 4 when necessary during an EECP event to ensure system reliability. |