To recommend approval of PRR749 as recommended by PRS in the corrected PRS Recommendation Report, as amended by the 020408 FPL Energy comments, and as revised by TAC.
This Protocol Revision Request (PRR) provides changes in wording, REC account qualification, REC award formulas and the introduction of compliance premiums to comply with . P.U.C. Subst. R. 25.173.
Reason:
To be compliant with August 26,2007 updates to P.U.C. Subst. R. 25.173. The rule changes were mandated by Senate Bill 20 (2005) and PUC rule making project 33492.