MIS LOG IN

PRR775

Summary

Title Change the name of Emergency Electric Curtailment Plan (EECP) to Energy Emergency Alert (EEA)
Next Group
Next Step
Status Approved on 12/09/2008
Effective Dates
05/01/2009

Action

Date Gov Body Action Taken Next Steps
12/09/2008 BOARD Approved
11/06/2008 TAC Recommended for Approval ERCOT Board consideration of PRR775
10/23/2008 PRS Recommended for Approval TAC consideration of PRR775
09/24/2008 PRS Recommended for Approval PRS Impact Analysis review

Voting Record

Date Gov Body Motion Result
12/09/2008 BOARD To approve PRR775 as amended by OWG comments. Passed
11/06/2008 TAC To recommend approval of PRR775 as recommended by PRS. Passed
10/23/2008 PRS To endorse and forward the PRS Recommendation Report and Impact Analysis for PRR775 to TAC with a new proposed effective date of May 1, 2009. Passed
09/24/2008 PRS To recommend approval of PRR775 as amended by ERCOT comments. Passed

Background

Status: Approved
Date Posted: Aug 22, 2008
Sponsor: ERCOT
Urgent: No
Sections: 2.1, 2.2, 5.6.6.1, 5.6.6.2, 5.6.7, 5.6.7.1, 5.6.8, 5.7, 5.8, 6.1.13, 6.5.2, 6.5.12, 6.7.3, 6.7.9, 6.10.2, 6.10.3.2, 6.10.6, 6.10.13.3
Description: This Protocol Revision Request (PRR) changes the name of the Emergency Electric Curtailment Plan (EECP) to Energy Emergency Alert (EEA).
Reason: Recent changes at the North American Electric Reliability Council (NERC) have increased the reporting, communications and compliance efforts at ERCOT. ERCOT is proposing these revisions in order to align terminology and reduce confusion when reporting events to NERC and the Federal Energy Regulatory Commission (FERC). Every step in the current EECP uses the term "curtailment," but ERCOT does not actually shed firm Load until the last step of EECP. The proposed revisions will align ERCOT and NERC terminology and reduce confusion when communicating statuses or reporting on recent events.

Key Documents

Related Content