To recommend approval of PRR788 as amended by Luminant comments and as revised by PRS.
Passed
Background
Status:
Approved
Date Posted:
Dec 9, 2008
Sponsor:
FPLEnergy
Urgent:
Yes
Sections:
6.5.13
Description:
This PRR proposes a requirement that certain existing WGRs limit the unit ramp rate to ten percent (10%) per minute of their nameplate capacity ratings as registered with ERCOT.
Reason:
This PRR is a follow-up to PRR771, which required ramp rate limitations for WGRs with signed Interconnection Agreements on or after Jan. 1, 2009. This PRR addresses units with signed Interconnection Agreements prior to Jan. 1, 2009.