PRR795
Summary
Title | 90-Day Transmission Outage Scheduling Timeline |
---|---|
Next Group | |
Next Step | |
Status | Approved on 02/17/2009 |
Effective Dates |
03/01/2009
|
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
02/17/2009 | BOARD | Approved | |
02/05/2009 | TAC | Recommended for Approval | Board Consideration |
01/22/2009 | PRS | Recommended for Approval | TAC Consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
02/17/2009 | BOARD | Approve PRR795 as recommended by TAC. | Passed |
02/05/2009 | TAC | To recommend approval of PRR795 as recommended by PRS. | Passed |
01/22/2009 | PRS | To endorse and forward the PRS Recommendation Report and Impact Analysis for PRR795 to TAC. | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Jan 5, 2009 |
Sponsor: | ERCOT |
Urgent: | Yes |
Sections: | 8.3.3 |
Description: | This Protocol Revision Request (PRR): 1) Adds a new Outage response timeline that will place a requirement on ERCOT to coordinate Outages submitted with more than ninety (90) days notice at least seventy-five (75) days prior to the start of the proposed Outage; and 2) Provides clarification of three (3) to eight (8) day timeline to eliminate an overlap in requirements. |
Reason: | 1) The ERCOT TCR case development process incorporates Outages submitted a minimum of forty-five (45) days before their planned start. Currently, ERCOT has no obligation to review any Outage more than thirty (30) days prior to the start of the proposed Outage. The new timeline will increase the accuracy of the TCR Outage by assuring all Outages included in the monthly TCR model have been coordinated. 2) Original language was confusing in that it appeared that the first two (2) timelines overlapped each other. |