To recommend approval of PRR815 as amended by PUCT Staff comments.
Passed
Background
Status:
Approved
Date Posted:
Jun 10, 2009
Sponsor:
ERCOT
Urgent:
Yes
Sections:
7.2, 7.2.1, 7.2.2, 7.2.3
Description:
This Protocol Revision Request (PRR) clarifies the process used to determine Commercially Significant Constraints (CSCs).
This PRR also proposes non-substantive administrative changes, such as correcting acronym and defined term usage and section references. These are shown below with the author "ERCOT Market Rules."
Reason:
As a result of PUCT Docket No. 36416, AEP Energy Partners’ Appeal of the Decision of the ERCOT Board Assigning Oklaunion Generating Station to the West Zone and Request for Expedited Consideration and Emergency Remand with Instructions, ERCOT was instructed by the PUCT to add clarity to the Commercially Significant Constraints (CSCs) process outlined in Protocol Sections 7.2.1 and 7.2.2.