PRR824

Summary

Title Primary Frequency Response from WGRs
Next Group
Next Step
Status Approved on 12/15/2009

Action

Date Gov Body Action Taken Next Steps
12/15/2009 BOARD Approved
11/05/2009 TAC Recommended for Approval ERCOT Board Consideration
10/22/2009 PRS Recommended for Approval TAC Consideration
09/17/2009 PRS Recommended for Approval PRS IA Review
08/25/2009 PRS Deferred/Tabled PRS Language Consideration

Voting Record

Date Gov Body Motion Result
12/15/2009 BOARD To approve PRR824 as recommended by TAC in the 11/5/09 TAC Recommendation Report Passed
11/05/2009 TAC To recommended approval of PRR824 as recommended by PRS in the 10/22/09 PRS Recommendation Report and as revised by the 10/28/09 ERCOT comments Passed
10/22/2009 PRS To endorse and forward the 9/17/09 PRS Recommendation Report as revised by PRS and Impact Analysis to TAC Passed
09/17/2009 PRS To recommend approval of PRR824 as amended by the 9/16/09 CPS Energy comments and as revised by PRS Passed
08/25/2009 PRS To table PRR824 for one month Passed

Background

Status: Approved
Date Posted: Jul 21, 2009
Sponsor: Rick Keetch on behalf of the Reliability and Operations Subcommittee (ROS)
Urgent: No
Sections: 2.1, 5.9.1.1, 5.9.1.3 (new)
Description: This Protocol Revision Request (PRR) adds a requirement for wind generator control systems to be programmed to respond to frequency deviations by controlling WGR real power output in a way that is similar to governor response for conventional generators.
Reason: As WGRs displace more and more conventional generation, there will be a growing need for WGRs to replace the primary frequency response capability not being provided by the Off-line conventional generators. WGR primary frequency response shall be of particular value if frequency increases occur.