PRR845
Summary
Title | Definition for IDR Meters and Optional Removal of IDR Meters at a Premise Where an Advanced Meter Can be Provisioned |
---|---|
Next Group | |
Next Step | |
Status | Approved on 07/20/2010 |
Effective Dates |
08/01/2010
|
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
07/20/2010 | BOARD | Approved | |
06/03/2010 | TAC | Recommended for Approval | ERCOT Board for consideration. |
05/20/2010 | PRS | Recommended for Approval | TAC for consideration. |
04/22/2010 | PRS | Recommended for Approval | PRS for Impact Analysis review. |
03/18/2010 | PRS | Deferred/Tabled | PRS for Impact Analysis review. |
02/18/2010 | PRS | Recommended for Approval | PRS for Impact Analysis review. |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
07/20/2010 | BOARD | To approve PRR845 as recommended by TAC in the 6/3/10 TAC Report. | Passed |
06/03/2010 | TAC | To recommend approval of PRR845 as recommended by PRS in the 5/20/10 PRS Report.All Market Segments were present for the vote. | Passed |
05/20/2010 | PRS | To endorse and forward the 4/22/10 PRS Report and Impact Analysis for PRR845 to TAC. | Passed |
04/22/2010 | PRS | To recommend approval of PRR845 as amended by the 4/8/10 RMWG comments. | Passed |
03/18/2010 | PRS | To table PRR845. | Passed |
02/18/2010 | PRS | To recommend approval of PRR845 as amended by the 2/9/10 ERCOT comments. | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Jan 22, 2010 |
Sponsor: | Terry Bates on behalf of the Retail Metering Working Group (RMWG) |
Urgent: | No |
Sections: | 2.1, 2.2, 6.5.12, 6.10.5.2, 6.10.13.1, 6.10.13.3, 9.2.5, 9.2.6, 9.2.6.1, 9.9, 10.2.2, 10.3.2.3, 10.3.3.3, 10.9, 10.9.1,10.9.2, 10.9.3, 18.6, 18.6.1, 18.6.2, 18.6.3, 18.6.4, 18.6.5, 18.6.6, 18.6.7 |
Description: | This Protocol Revision Request (PRR) clarifies the meaning of Interval Data Recorder (IDR) Meter and provides for optional removal of IDR Meters under certain conditions for Premises where an Advanced Meter can be provisioned by the Transmission and/or Distribution Service Provider (TDSP). In addition, due to the proposed definition of an IDR Meter, Protocol references to IDR and/or IDR Meter are being updated to ensure appropriate understanding and usage of the terms. This PRR also proposes non-substantive administrative changes, such as correcting acronym and defined term usage and section references. |
Reason: | This PRR provides guidelines for the installation and removal of an IDR Meter as it relates to the use of provisioned Advanced Meters. |