Title | Additional Exemptions for Uninstructed Resource Charge |
---|---|
Next Group | |
Next Step | |
Status | Approved on 08/17/2010 |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
08/17/2010 | BOARD | Approved | |
08/05/2010 | TAC | Recommended for Approval | Board consideration |
07/20/2010 | BOARD | Remanded | TAC consideration |
07/01/2010 | TAC | Recommended for Approval | ERCOT Board consideration |
06/17/2010 | PRS | Recommended for Approval | TAC consideration |
05/20/2010 | PRS | Recommended for Approval | PRS consider the PRS Recommendation Report and Impact Analysis |
04/22/2010 | PRS | Deferred/Tabled | PRS consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
08/17/2010 | BOARD | To approve PRR847 as recommended by TAC in the 8/5/10 TAC Report. | Passed |
08/05/2010 | TAC | To recommend approval of PRR847 as recommended by TAC in the 7/1/10 TAC Report. All Market Segments were present for the vote. | Passed |
07/20/2010 | BOARD | To remanded PRR847 to TAC. | Passed |
07/01/2010 | TAC | To recommend approval of PRR847 as recommended by PRS in the 6/17/10 PRS Report with a proposed effective date of August 1, 2010. | Passed |
06/17/2010 | PRS | To endorse and forward the 5/20/10 PRS Report as amended by the 6/7/10 ERCOT comments as revised by PRS and Impact Analysis for PRR847 to TAC. | Passed |
05/20/2010 | PRS | To recommend approval of PRR847 as amended by the 5/13/10 Formosa Utility Venture comments. | Passed |
04/22/2010 | PRS | To table PRR847 | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Mar 15, 2010 |
Sponsor: | Formosa Utility Venture, Ltd |
Urgent: | No |
Sections: | 6.8.1.15.1 |
Description: | This Protocol Revision Request (PPR) proposes two changes to Section 6.8.1.15.1 as follows: 1. When a Qualified Scheduling Entity (QSE) is given a verbal Dispatch Instruction from ERCOT, the QSE shall be exempt from any Uninstructed Resource Charge during the specified verbal Dispatch Instruction time period, provided that the QSE followed instructions to within the Schedule Control Error (SCE) of the verbal Dispatch Instruction given. 2. After a Load acting as a Resource (LaaR) has been activated, the QSE representing the LaaR can request a three hour extension for scheduling under paragraph (11) of Section 6.10.6, Ancillary Service Deployment Performance Conditions, and during this rescheduling time, a Private Use Network shall not incur Uninstructed Resource Charges for three hours as the Load returns back to service. Additional non-substantive administrative revisions, such as correcting defined term usage, number usage and paragraph references, are shown with the author "ERCOT Market Rules." |
Reason: | The two reasons for the proposed revisions are as follows: 1. Under the current Protocols, QSEs have received Uninstructed Resource Charges when following verbal Dispatch Instructions issued by ERCOT, even though they followed such instructions precisely. 2. Private Use Networks are unfairly penalized with Uninstructed Resource Charges until the Load is restored. The co-generation site is unable to shed generation as there is a consistent Real Time steam demand, therefore the Private Use Network will run an SCE until the Load is restored. Formosa Utility Venture, Ltd. has incurred several Uninstructed Resource Charges after successful deployment of LaaRs in the past. |
Key Documents
Mar 15, 2010 - doc - 92.5 KB
Mar 16, 2010 - doc - 44 KB
Apr 21, 2010 - doc - 41.5 KB
Apr 26, 2010 - doc - 90 KB
May 13, 2010 - doc - 43 KB
May 24, 2010 - doc - 93.5 KB
May 26, 2010 - doc - 67.5 KB
Jun 7, 2010 - doc - 45.5 KB
Jun 8, 2010 - doc - 44 KB
Jun 21, 2010 - doc - 99.5 KB
Jul 6, 2010 - doc - 101.5 KB
Jul 21, 2010 - doc - 103 KB
Aug 6, 2010 - doc - 103.5 KB
Aug 17, 2010 - doc - 103.5 KB