Title Process Change for Review of Impact Analysis on Point to Point Transactions or Processes Between CRs and TDSPs That Have No Impact to ERCOT
Next Group
Next Step
Status Approved on 02/05/2009
Effective Dates
03/01/2009

Action

Date Gov Body Action Taken Next Steps
02/05/2009 TAC Approved
01/14/2009 RMS Recommended for Approval For TAC consideration.
12/10/2008 RMS Recommended for Approval RMS for Impact Analysis Review

Voting Record

Date Gov Body Motion Result
02/05/2009 TAC To recommend approval of RMGRR071 as recommended by RMS. Passed
01/14/2009 RMS To endorse and forward the RMS Recommendation Report and Impact Analysis to TAC. Passed
12/10/2008 RMS To recommend approval of RMGRR071 as amended by ERCOT comments and as revised by RMS. Passed

Background

Status: Approved
Date Posted: Nov 13, 2008
Sponsor: Rob Bevill and Kathy Scott on behalf of the Texas SET Working Group
Urgent: No
Sections: 3.3.3, 3.3.5
Description: This Retail Market Guide Revision Request (RMGRR) allows for the Impact Analysis of RMGRRs that are limited to Point to Point transactions or processes between Competitive Retailers (CRs) and Transmission Distribution Service Providers (TDSPs) that have no impact to ERCOT to be reviewed and approved by the Retail Market Subcommittee (RMS) at the RMS meeting at which the RMGRR is first considered.
Reason: This RMGRR allows for the Impact Analysis of RMGRRs that involve CRs and TDSPs only in their Point to Point transactions or processes to be reviewed and approved by RMS at the same meeting, allowing the RMGRR to proceed through the stakeholder process without being delayed until the next RMS meeting.